Current Construction

0

Towne Road and 106th Street

WHEN: Closed May 30

WHAT: Roundabout construction

DURATION: Estimated to take 45 days

 

Hazel Dell Parkway and 116th Street

WHEN: Closed on or after June 5

WHAT: Roundabout construction

DURATION: Estimated to take 75 days

 

City Center Drive and Range Line Road

WHEN: Closed on or after June 5

WHAT: Roundabout construction

DURATION: Estimated to take 14 days, after which time, there will continue to be partial closures of the intersection until completion, which is anticipated to be on or prior to July 1.

 

136th Street and Gray Road

WHAT: Roundabout Construction

DURATION: Expected to open in mid-June.

 

Carmel Drive and City Center Drive

WHAT: Roundabout construction

DURATION: Expected to open mid-June.