The Campus Parkway interchange was recently shifted into a double-crossover traffic pattern. The interchange will remain under construction through July. (Submitted image)

The Campus Parkway traffic pattern at Interstate 69’s Exit 210 interchange will be shifted for the third phase of construction beginning June 14.

In order to implement the traffic pattern changes, Milestone Contractors plans to temporarily close Campus Parkway access over I-69 and some interchange ramps starting at 9 p.m. Wednesday, June 14. Electronic message signs and police will direct motorists to the Olio Road overpass to cross over the interstate during the overnight traffic pattern change.

Weather permitting, Campus Parkway is expected to be open to traffic by 6 a.m. Thursday, June 15. Phase 3 traffic changes include:

  • Westbound traffic will be shifted to the south side of the bridge over I-69
  • A second lane will be opened on eastbound Campus Parkway to southbound I-69
  • Slightly altered lane alignments and intersection locations at interchange ramps
  • New traffic signals will replace temporary yield signs at some interchange ramps.

The Campus Parkway interchange was recently shifted into a double-crossover traffic pattern. The interchange will remain under construction through July, when it is expected to be fully open to traffic in its permanent configuration.

Multiple traffic lane shifts will be required to complete construction of the new interchange design. Each phase of remaining construction will bring the interchange closer to its final traffic configuration and capacity.